January 23, 2025

Flex Tech

Innovation in Every Curve

Innovative solutions emerge to reduce 2.5-TW US clean energy interconnection backlog

Innovative solutions emerge to reduce 2.5-TW US clean energy interconnection backlog

The still growing backlog of generation projects in U.S. transmission provider interconnection queues may soon be relieved by emerging innovative solutions.

Proposed generation and storage awaiting interconnection is about twice the estimated 1,280 GW of U.S. generation capacity, according to an April Lawrence Berkeley National Laboratory report. And while projects built before 2015 had taken “about 17 months” to go from application to operation, that time was “approaching 5 years for projects completed in 2022-2023,” the report said.

But in response to Federal Energy Regulatory Commission Order 2023, approved in July 2023, U.S. transmission providers and system operators have been developing new solutions.

FERC Order 2023 established some important new requirements for interconnection that update a 20-year-old process, said LBNL Energy Policy Researcher Joseph Rand. “It prioritizes more viable projects that have met readiness criteria and imposes financial penalties that require both transmission providers and system operators to step up their game,” he added.

But FERC’s order only begins to address the streamlining of the project interconnection process needed to meet newly growing loads, regulators and stakeholders agree.

Order 2023 “is an important step forward in the effort to address interconnection backlogs,” wrote former FERC Commissioner Allison Clements in her concurrence to its approval. But transmission providers, interconnection customers and other stakeholders should “consider the rule’s requirements a strong baseline and not a ceiling,” and develop further reforms, she added.

The Texas “connect and manage” streamlined interconnection option may prove viable in its energy only market, analysts said. And SPP’s work to link system planning with the interconnection process across its multi-state region could be a breakthrough in reducing queue backlogs when it is complete, they added.

California, with its just-approved interconnection enhancements, leads the innovation because it is already linking transmission planning and generation procurement with the project interconnection process, stakeholders agreed. But scoring of projects’ viability, commercial readiness and system value may not balance the needs of utilities and developers and may impede meeting load growth, some said.

California’s innovative enhancements

The CAISO Board voted 5-0 on June 12 to move ahead on identifying and prioritizing project interconnection where planning shows “transmission capacity exists or new transmission has been approved,” according to the just-approved plan. The enhancements are designed to interconnect projects with the most operational readiness and commercial and system value, the board added.

CAISO’s plan identifies “zones” where transmission capacity is available or will be built, said CAISO Principal of Infrastructure Policy Development Danielle Mills.

This zonal approach “is the cornerstone of the whole reform effort,” and other “procedural reforms” are to “enable the new approach,” Mills said. The plan guides developers to “transmission plan deliverability” zones with available transmission identified in CAISO planning, and gives utilities and other load-serving entities, or LSEs, incentives to procure those projects, she added.

backlog

Permission granted by CAISO

 

Projects will earn 35% of their total “score” based on viability criteria, such as control of the proposed site and completeness of the engineering design. The project’s value as system-wide or local resource adequacy will determine another 35% of its score.

Demonstrated commercial interest by LSEs in a project will determine the remaining 30% of the score, though that could give LSEs negotiating leverage over developers who need LSE interest to score higher, both CAISO and stakeholders acknowledged.

In each zone, CAISO will select projects with the highest scores to study in detail, with the project’s value to the zone’s local distribution system as the first tiebreaker, Mills continued. For projects still tied, “the developer willing to pay more in a sealed-bid auction to have an interconnection study done wins and moves its project into the study process,” she said.

link